Category Archives: CIOB

New CIOB Contract for Complex Projects

The Chartered Institute Of Building (CIOB) has launched a new contract for construction and engineering projects. The CIOB Contract for Complex Projects has been written for the 21st Century. It is designed to permit the CIOB’s Guide to Good Practice in the Management of Time in Complex Projects to be put into practice.

The contract can be used for collaborative design with a building information model (BIM) and anticipates and encourages competence in the use of computerised transmission of data. It requires collaborative working in the management of risks and transparency of data used in such management.

The contract has been drafted to be used in any country and legal jurisdiction around the world to provide a means of managing the causes and consequences of delay (the single most common cause of uncontrolled loss and cost escalation in complex building and engineering projects) where the design is produced by the employer, the contractor with or without a building information model.

The key principles embedded in the contract design include:

  • It is written in plain English, suitable for both building and engineering projects and may be adopted for other types of work. It can be used for turnkey, design and build, for construction only, or for part contractor’s design, both in the UK and internationally.
  • It permits a variety of contract documents including BIM (building information model) and requires electronic communications either via a file transfer protocol or a common data environment for collaborative working.
  • The contract contains new roles for the Project Time Manager, Design Coordination Manager and Auditor, as well as the Contract Administrator and the design team.
  • It requires complete transparency in planned and as-built information in compliance with the CIOB’s Guide to Good Practice in the Management of Time in Complex Projects. It is currently the only standard form of contract available which requires a resourced critical path network, a planning method statement and progress records to a specified, quality assured standard, with significant redress for a failure to comply with the contract requirements.
  • The contractor’s schedule (or programme as it is called in other contracts) is to be a dynamic critical path network in varying densities, described and justified in a planning method statement. It is to be designed in different densities compatible with the information available, reviewed and revised in the light of better information as it becomes available, updated with progress and productivity achieved and resources used and impacted contemporaneously to calculate the effect of intervening events on time and cost (see more on Schedule Density).
  • The contractor’s schedule is not only the time control tool but also the cost control tool against which interim valuations are made and the predicted cost of the works is calculated contemporaneously permitting out-turn cost and total time prediction on a daily basis though the updated working schedule.
  • The contract contains detailed requirements for the identification and use of time and cost contingencies, defines float and concurrency and sets down rules for their use. It provides the power for the contractor to keep the benefit of any time it saves by improved progress as its own contingency, which cannot be taken away.
  • It contains a procedure for contemporaneous expert resolution of issues arising during construction. In the absence of reference to experts specified issues concerning submittal rejections and conditional approvals are deemed to be agreed, helping to avoid doubt about responsibilities and escalation of disputes. The experts used during the course of the works can be called as a witness by either party in any subsequent adjudication and/or arbitration proceedings and, in order to help to give transparency to the way dispute resolvers deal with the contract and help to make sure it functions in the way it is supposed to, the adjudicator’s decision and/or arbitrator’s award is to be a public document, unless the parties agree otherwise.

The Chartered Institute of Building would like to receive your comments and criticism on the Review Edition of the CIOB Contract by Monday, 30 July 2012. All comments will be acknowledged and taken into consideration in future review and revision of the form and its constituent standard form documents. To review the contract see: http://www.ciob.org.uk/CPC

Lessons Learned

The London Olympic Delivery Authority’s Learning Legacy is designed to facilitate the dissemination of the lessons learned from the London 2012 construction project for the benefit of future projects and programmes, academia and government with the intention of raising the bar within the construction sector.

The ODA are on the verge of delivering a massive program of works on-time and on-budget, the learning from this major undertaking can benefit everyone.  To browse and download the 250 documents see: http://learninglegacy.london2012.com/

There are four types of reports:

    • Micro reports: Short examples of lessons learned, best practice and innovations from the construction programme.
    • Case studies: Peer reviewed papers on lessons learned, best practice and innovations from across the Programme.
    • Research summaries: Summary reports of research projects undertaken by academia and industry on the London 2012 construction.  These organisations will also publish full research papers as they are finalised throughout 2012.   Over 600 interviews were undertaken by researchers on the ODA and its supply chain as part of the learning legacy research.
    • Champion products: Examples of tools and templates used successfully on the programme.

    The reports have been classified into 10 themes:

  • Programme and project management;
  • Design and engineering innovation
  • Equality, inclusion, employment and skills;
  • Health and safety;
  • Masterplanning and town planning;
  • Procurement and supply chain management;
  • Sustainability;
  • Systems and technology;
  • Transport;
  • Archaeology.

This is a highly recommended rich source of information.

Carbon Action 2050

The negative approach to carbon reduction emanating from sections of Australian industry and political structure is to say the least short sighted and disappointing, particularly given the devastating floods and cyclones of the last year or two. These local changes have been repeated by tornados, hurricanes and floods around the world.

For anyone to suggest the climate is not changing is simply ignoring the facts. Defining the cause of change may be more debatable. Correlation is not causation! From a pragmatic viewpoint man made carbon pollution may be causing the change in the climate, contributing to the change or simply polluting the atmosphere without any effect.

Depending on which of the three options is correct, cleaning up our carbon footprint to levels the natural systems can absorb will either, solve the climate change problem, reduce the climate change problem or merely reduce our contamination of the environment we live in.

However, not taking appropriate and immediate action on carbon pollution will either, push the climate change problem to greater extremes, increase the effect of climate change or simply continue to contaminate the environment we live in.

From a risk management perspective, doing nothing or minimal change is not really a sensible option until there is conclusive proof that carbon has no effect on the weather and sea levels. That proof has not been demonstrated by anyone, and whilst proof that carbon is adding to the climate change problem is far from conclusive, the strong weight of evidence is trending to support the view carbon is either the cause of the change or a major contributor to the change.

The very short term arguments raised by miners, industry and some politicians that doing anything is too expensive ignores the long term costs to every industry in favour of the next quarterly profit statement –ignoring the impact of floods, cyclones and rising sea levels on profits and value generation.

Outside of Australia, practical action is being taken by a wide range of organisations. The Chartered Institute of Building – CIOB – has launched Carbon Action 2050, a free interactive online tool that provides key guidance on every facet of a building’s lifecycle from design through construction to end use and beyond.

There is advice on education, skills and leadership and how to move those agendas towards a low carbon built environment. The portal has been developed over the last twelve months by CIOB members who work in design, building control, education, project management, facilities management, conservation and sustainability. Its overall aim is to focus on innovation and best practice that will make an immediate difference on the ground. To find out more visit: http://www.carbonaction2050.com/

Locally, we need to start taking similar actions, as a minimum we will start cleaning up our mess, more likely we will contribute to saving the planet (or at least reducing the impact of climate change)!

Biased Book Reviews

I sometimes wonder if the total freedom of the internet is an asset. Over the last several years I’ve been working with a tem of international experts to develop the CIOB Guide to Good Practice in the Management of Time in Complex Projects. We are now developing a certification framework to help support the development of a proper career framework for schedulers (for more on this see: http://www.mosaicprojects.com.au/Training-CIOB-TM_Credential.html).

The Guide was developed for a specific purpose that is clearly enunciated in the marketing materials. The description is: The first stage, this [book], sets down the process and standards to be achieved in preparing and managing the time model. As a handbook for practitioners it uses logical step by step procedures and examples from inception and risk appraisal, through design and construction to testing and commissioning, to show how an effective and dynamic time model can be used to manage the risk of delay to completion of construction projects.

As a guide for practitioners the book has limitations, in particular it is not intended to be an academic text. Then you read the review on Amazon UK from an anonymous ‘Richard and his cat’ and he complains the book:

  • is written in bad english - very insightful as good English requires correct capitalisation as a minimum. The language in the book is not complex academic English primarily because its audience is world wide.
  • is full of unsubstantiated opinion and without any academic referencing to evidence – absolutely correct! This is a guide for practitioners.
  • appears to be written from the slanted viewpoint of an employers delay analysis consultant who wants an easy life by having the contractor do his work for him – I have no idea what ‘Richard’ does for a living but I always thought the job of the contractors scheduler was to make the employers consultants life as easy as possible by developing fully substantiated claims that can be approved un-amended. The Guide does strongly advocate keeping good records; these are needed for legitimate claims.
  • if a MSc Thesis then it would be a failure – completely agree! A MSc Thesis requires a very structured format and generally prohibits new ideas and thinking – the thesis has to be built on established writings. The Guide takes a radically new look at how to implement effective time management in complex projects and is written to be read and used.

Fortunately some newer reviews are appearing. The Guide will undoubtedly improve when the second edition is developed in a couple of years. For now I think it has a lot to offer practical project managers, schedulers and planners, but then I’m biased, I know the calibre of the people involved in developing The Guide.

PMI-SP and PTMC Courses Launched

Mosaic is offering a world-first integrated scheduling course for the PMI Scheduling Professional (PMI-SP) and CIOB Project Time Management Certificate (PTMC). The total course comprises 13 modules of focused schedule training.

Modules 1 to 6 provide the education needed for the new CIOB Project Time Management Certificate (PTMC) examination.

Modules 1 to 5 plus Modules 7 to 13 provide the education needed for the PMI-SP credential.

All of the modules are available via Mosaic’s Mentored Email™ delivery allowing schedulers to prepare for their examinations anywhere, any time.

Additionally, Modules 1 to 4 are incorporated into Mosaic’s successful 1 Day and 2 Day scheduling workshops. The 1 Day workshop is exclusively focused on the exam-prep modules, the 2 Day workshop covers a range of additional scheduling and time management topics.

Bookings for this exciting range of courses are open with module delivery scheduled from the 1st March for the Mentored Email™ courses.

The first 1 Day workshop focused on the new courses will be held on the 12th April in Melbourne with others to follow.

Details of our one-on-one Mentored Email™ course are at http://www.mosaicprojects.com.au/Training-Planning_One-on-One.html.

Our first 1 Day classroom course incorporating modules 1 to 4 will be in Melbourne, Australia on the 12th April, for more on the classroom courses see: http://www.mosaicprojects.com.au/Training-PMGen%205-STEPS.html

For more information on the CIOB Project Time Management Certificate (PTMC) and course fees see: http://www.mosaicprojects.com.au/Training-CIOB-TM_Credential.html

For more information on the PMI Scheduling Professional credential (PMI-SP) and course fees see: http://www.mosaicprojects.com.au/Training-Planning.html

If you wish to buy a copy of The Guide in advance of the course, see: http://www.mosaicprojects.com.au/Book_Sales.html#CIOB – your course fees are reduced if we don’t have to ship books.

Guide to Good Practice in the Management of Time in Complex Projects

Wiley and the Chartered Institute of Building have just published a new book, the Guide to Good Practice in the Management of Time in Complex Projects. The primary purpose of this Guide is to set down the standards necessary to facilitate the effective and competent management of time in complex projects. It defines the standards by which project schedules will be prepared, quality controlled, updated, reviewed and revised in practice and describes the standards of performance which should reasonably be required of a project scheduler.

Delayed completion affects IT, process plant, oil and gas, civil engineering, shipbuilding and marine work contracts. In fact it affects all industries in all countries and the bigger the project, the more damage delayed completion causes to costs, to reputation and sometimes, even to the survival of the contracting parties themselves.

In simple projects, time can be managed intuitively by any reasonably competent person, but complex projects cannot and a more analytical approach is necessary if the project is to succeed. Although much has been written about how to apportion liability for delay after a project has gone wrong there was, until recently, no guidance on how to manage time pro-actively and effectively on complex projects.

The Guide has been developed as a scheduling reference document capable of wide application. It is a practical treatise on the processes to be followed and standards to be achieved in effective management of time. It can be used in any jurisdiction, under any form of contract, with any type of project and should be identified as the required standard for the preparation and updating of contract programmes, progress reporting and time management.

I may be biased, my partner was part of the team that developed The Guide and it recognises the importance of involving stakeholders in the development of the schedule, but I feel it has a lot to offer project planners and schedulers on any type of project.

For more information;
in Australia see: http://www.mosaicprojects.com.au/Books.html#CIOB_Guide elsewhere, http://eu.wiley.com/WileyCDA/WileyTitle/productCd-144433493X.html

Definition of Construction Management

Developing definitions for context sensitive processes such as project management is difficult [see paper]. Over the last year I have had involvement with the efforts of the CIOB UK to develop a similar type of definition for Construction Management. The final definition is rather long, but is I would suggest both accurate and concise.

Construction Management is: The management of the development, conservation and improvement of the built environment; exercised at a variety of levels from the site and project, through the corporate organisations of the industry and its clients, to society as a whole; embracing the entire construction value stream from inception to recycling, and focusing upon a commitment to sustainable construction; incorporating a wide range of specialist services; guided by a system of values demonstrating responsibility to humanity and to the future of our planet; and informed, supported and challenged by an independent academic discipline.

The result of this work is now available for download and sets the benchmark for project mangers to aspire to achieve [download the CM definition].

More thoughts on Expo 2010

One of the interesting juxtapositions around Expo 2010 is its theme of sustainability contrasted to a massive temporary exhibition focused on an intensive 6 months with much of the site to be demolished in October.

The Expo is certainly a success with a projected attendance of 75million visitors. From the sustainability perspective there have been many innovations and initiatives.

Much of the heating and cooling uses heat pumps powered by solar (PVC) cells. Movement across the site has been optimised in three planes, above on, and below ground encouraging walking and most of the transportation is electric powered. Several of the larger buildings are designed for re-use and one incorporates the world’s largest green wall. Another innovation has been refurbishing many of the pre-existing industrial buildings on-site to preserve Shanghai’s heritage.

The Expo is also hosting a string of conference events focusing world experts on its theme of ‘better city, better life’ and sustainability. This was also a key focus of the CIOB events we attended.

The World's Largest 'Greenwall' diring construction. Now it's a mass of green.

Part way through, it’s hard to assess if the Expo will contribute a net benefit to sustainability and ‘better city’ development but from what we saw, it is looking positive.

Before moving onto other topics though, there were many pavilions that really caught our attention. The Chinese and UK pavilions have already been mentioned. The Australian pavilion is a standout design looking like cross between Ayres Rock and a tin shed. The design is very distinctive and ‘Australian’.

The Australian Pavilion

Many of the countries used interesting cladding to focus on sustainability and insulation. The Canadian pavilion was covered in lumber, the Portuguese in cork. The ‘paper cut’ effect of the Polish pavilion combined a classic Chinese art from with shading and ventilation.

The Polish Pavilion's 'Paper Cut'

Overall the experience was fantastic, as long as you don’t mind the crowds, and will be long remembered. Thoughts on sustainability and ‘Zero Carbon’ will follow in later posts.

CIOB Shanghai Meetings

The Chartered Institute of Building for the first time in its 187 year history held its AGM, Board of Trustees and Members Forum meetings outside of the UK. In addition to the working meetings, the two highlights of a busy week were the International Construction Conference focused on sustainability and ‘zero carbon’ construction and a visit to World Expo 2010.

Shanghai Hotel (background) and Conference Venue

The business part of the week was centred in the impressive J.W. Marriott hotel and the adjacent Grand State Theatre. Given some time to reflect on these experiences, I intend writing a couple of posts focusing on some of the ideas and observations from the meetings and conference.

I want to focus this post on an incredible experience from World Expo. Lynda has described the size and intensity of the Expo in her post World Expo Shanghai 2010. And whilst the China Pavilion undoubtedly had the longest queues, another ‘long queue’ pavilion is the remarkable British ‘dandelion’. The design concept is that of a ‘gift’ to the Chinese people surrounded by its wrapping paper.

UK Pavilion

The wonderful fuzzy effect on the outside is created by 60,686 hand crafted acrylic rods, each 7 meters long which allow light into the inside of a 20 meter plywood cube.

Some of the 60,000 rods

Remarkably each rod has between 1 and 10 seeds embedded in the end representing Chinese plant species that are growing in the UK.

Some of the seeds embedded in the rods

The effect outside is fascinating, inside it is simply mind blowing. I have never experienced anything quite like this.

The effect inside

At one level the display is totally useless, at another the juxtaposition of 60,686 individually hand crafted rods focusing on plant seeds to the overall scale of the Expo simply has to be experienced. Judging from the fact over 1 million people a month are queuing for hours for the experience, I feel the UK designers have achieved their objective of raising the UK’s profile at all levels of Chinese society.

At the moment, plans are to demolish the pavilion in October and to distribute the section of each rod holding the seeds to schools and other institutions. I hope this changes and the ‘cube’ can be found a home intact somewhere in the city for future generations to experience.

World Expo Shanghai 2010

I have just finished a week in Shanghai; the main purpose of my trip was to participate in a panel session at the CIOB International Construction Conference. For more on this see Patrick’s post CIOB Shanghai Meetings. However, the highlight of the trip was a day spent at World Expo.

The Expo is simply enormous. The site covers a total area of 5.28 square kilometres spread along both sides of the Huangpu River in downtown Shanghai; it includes gardens, wet lands, paved walkways and 100s of new and renovated buildings.

In the two months since opening the Expo has hosted over 20 million visitors and expects over 75 million before closing in October. On busy days over half a million visitors are on the site. Everywhere you look on the site there are queues but the organisers keep things moving, the officials are polite and helpful and the crowd rubs along without friction, maybe even enjoying the experience. From a stakeholder management perspective, expectations are managed and information is readily available, particularly if you speak Mandarin – international visitors are not likely to exceed 5 million.

The China Pavilion dominates the site and is a wonderful experience. For locals to visit the pavilion, someone has to join the queue outside the gates at 6:00am to so when the gates open at 9:00am they can be near enough to the front of the next queue at the China Pavilion to receive some of the 50,000 tickets issued daily to allow them join another queue for 2 to 3 hours to get inside to see and experience the exhibits.

I was more fortunate, the hosts of the CIOB conference were able to arrange VIP access but I can understand why the Chinese pavilion is worth the wait. Its exhibits really are wonderful. There are over 200 countries and international organisations represented, ranging from Tuvalu to the USA; the World bank to the International Council of Museums, as well as numerous major corporations and most Chinese provinces. Almost every pavilion had its queue! In a long day I only managed to see a small section of the total experience but could start to appreciate the overarching purpose of this great festival.

My visit to the Expo was a once in a lifetime experience. If you can’t make the trip personally, you can be a virtual tourist on line at http://en.expo.cn/. Either way World Expo 2010 is well worth the visit.